W14_Anton_Depreciation


W14_Anton_Depreciation 1. Problem Recognition, Definition, and Evaluation On 2006 MPV car series 307 SW from Peugeot sold with price Rp. 498.000.000. on 2013 it sold on Rp. 200.000.000. What method to calculate depreciation? 2. Development of the Feasible Alternative Method … Continue reading

Posted in Anton | 1 Comment

W13_Anton_Comparison PERT and Monte Carlo


W13_Anton_Comparison PERT and Monte Carlo 1.      Problem Recognition, Definition, and Evaluation On blog W12.3, PERT method to define schedule contingency refer to risk identified, percentile desired is 90%. This week, using the same data, I would like to apply Monte … Continue reading

Posted in Anton | 1 Comment

W12.3_Anton_Schedule Risk Assessment


1.      Problem Recognition, Definition, and Evaluation Activities and duration estimate base on productivity and volume of work for earth work job as shown on table 1. Risks for those activities are identified and quantitative as shown on table2. Need to … Continue reading

Posted in Anton | 1 Comment

W12.2_Anton_Schedule Risk Assessment


1.      Problem Recognition, Definition, and Evaluation Activities and duration estimate base on productivity and volume of work for earth work job as shown on table 1. Risks for those activities are identified and quantitative as shown on table2. Need to … Continue reading

Posted in Anton | 1 Comment

W12.1_Anton_Schedule Contigency


1.      Problem Recognition, Definition, and Evaluation Base on productivity and volume of work for earth work job, duration of each activity for schedule development was calculated as on table1. Risk for those activities are identified and quantified as on table … Continue reading

Posted in Anton | 1 Comment

W12_Anton_Schedule Risk Assessment


1.      Problem Recognition, Definition, and Evaluation Base on productivity and volume of work for earth work job, duration of each activity for schedule development was calculated as on table1. Relation of activities was Finish to Start. Risk for those activities … Continue reading

Posted in Anton | 1 Comment

W11_Anton_Regression Linier for Estimation and Straight Line Method of Depreciation


1.      Problem Recognition, Definition, and Evaluation Refer to blog W10, Badu want to use other method to estimate natural rubber selling price, he conduct more research regarding rubber selling price and found data:   2.      Development of the Feasible Alternative … Continue reading

Posted in Anton | 1 Comment

W10_Anton_Project’s Economic Worthiness


1.      Problem Recognition, Definition, and Evaluation Many people in Badu home town said it good to have rubber plantation as an investment. Prior decided to investment he need to know is it feasible and how much return he could expect. … Continue reading

Posted in Anton | 1 Comment

W9.1_Anton_Developing Labor Rates


1.      Problem Recognition, Definition, and Evaluation A coal mining company was located in remote area in Indonesia have need to hire 10 engineers for a project at site with contract duration 1 year. They invite some manpower supply company to … Continue reading

Posted in Anton | 1 Comment

W9_Anton_Developing Labor Rates


W9_Anton_Developing Labor Rates 1.      Problem Recognition, Definition, and Evaluation A coal mining company was located in remote area in Indonesia have need to hire some staff and engineers for a project at site with contract duration 1 year. They invite … Continue reading

Posted in Anton | 1 Comment